This tower will be the tallest in the Sydney Olympic Park area standing at 25 storeys with 3 basements.  Our work commences at the bottom of Basement B3.

Australia Tower has 2 cores for lifts and stairs with the low rise core terminating at level 16, the high rise at level 25.

Fabquip designed, manufactured and hired the jumpform system for this project.

The surface area of the cores is approximately 7,000 sqm in total.  The expected commencement date for installation is mid May 2010 with an anticipated construction period for the core of 35 weeks.