The project consisted of 4 structures, generally at 40 metres in height (31.3 for Product Building), comprising:
Fabquip provided separate slipform equipment for the Production Building and the Cleaning Building as both buildings were on the critical path. As the silos were not on critical path we set up our equipment to complete the 10 silo structure before modifications were made to construct the 8 silo structure. The project commenced with our assembly of the Product Building in early November 2006 and was completed after stripping the slipform on the 8 silo structure in early June 2007.